Project Summary

Saqr General Contracting played a pivotal role in transforming and developing the surroundings of the historic Aqueduct Wall ( Magra Al-Ayoun) in Cairo. Over decades, the area had become heavily polluted with massive accumulations of waste and demolition debris. Saqr General Contracting undertook the monumental task of removing over 700,000 cubic meters of accumulated debris and garbage.

Leveraging state-of-the-art technology and employing a fleet of modern machinery—including loaders, dump trucks, excavators, and bulldozers—the company executed the project with precision and efficiency. To ensure the area was restored to its optimal condition, Saqr General Contracting also applied a layer of high-quality sand around the wall, effectively eliminating traces of waste and reinforcing the area's structural integrity and cleanliness.

This project stands as a testament to Saqr General Contracting’s commitment to preserving Egypt’s cultural heritage while utilizing advanced engineering practices to deliver exceptional results.

Scope of Work

  • Comprehensive Waste Removal:
  • Cleared over 700,000 cubic meters of demolition waste and garbage that had accumulated over more than three decades around the historic wall.
  • Deployment of Advanced Equipment:
  • Utilized a fleet of specialized vehicles and machinery, including:
    • Loaders for handling large quantities of debris.
    • Excavators for deep cleaning and demolition removal.
    • Dump Trucks for transporting waste to designated disposal sites.
    • Bulldozers for leveling and clearing the ground.
  • Site Preparation and Restoration:
  • Applied a layer of sand around the Aqueduct Wall to mitigate long-term effects of waste accumulation and prepare the area for future development or preservation.
  • Historic Preservation Focus:
  • Executed work under strict guidelines to preserve the structural and historical integrity of the Aqueduct Wall, ensuring no damage occurred to this invaluable landmark.

Clients

This project was executed for:

  • The New Urban Communities Authority

Project Duration

Saqr General Contracting successfully completed this ambitious project within a 6-month timeframe, showcasing the company’s ability to deliver superior results while adhering to tight deadlines.